Initial Environmental Evaluation of Alternative Methods to Conserve Rupa Tal Lake, Nepal

Christopher M. R. Pastakia & Jesper Bay

(reprinted from “Environmental Impact Assessment using the Rapid Impact Assessment Matrix (RIAM)) ed. Kurt Jensen. Olsen & Olsen, Fredensborg, Denmark. 1998)

 

 

Abstract The paper describes an Initial Environmental Evaluation (IEE) that was undertaken to assess the various alternative interventions that might be carried out to conserve or improve the existing lake and valley of Rupa Tal,Nepal. The project was undertaken in a short field visit, which allowed a reconnaissance of the area and direct discussions for the views and experiences of local people. This data was analysed using the Rapid Impact Assessment Matrix (RIAM) which allowed a sound basis for comparison of alternatives.

Four alternative options were considered: a ‘no action’ situation which would result in complete sedimentation of the lake save for a central river channel; a high dam on the southern margin to raise and maintain the water levels above the existing level; a shorter, high dam within the existing lake area with the same objective as the previous option; and a large sediment dam or series of sediment-holding cascades to prevent sedimentation of the remaining body of the lake.

 

The IEE was able to define a series of important components for comparison of these options, and the RIAM demonstrated the variation in impact that each option would produce. The IEE shows that the RIAM is an effective and rapid method to arrive at holistic comparison of strategic options in planning. From the RIAM results it has been possible to show that the mid-lake dam provides little additional benefit to the southern margin dam. The latter has a number of negative sociological and economic/operational impacts, but also significant positive benefits. A detailed in-depth EIA would be needed before proceeding with this option.

The option of providing up-stream sedimentation was shown to be the least disruptive option, though with negative impacts in operational and maintenance costs and implementation. This was the most likely option to maintain the present shape and form of the lake.

 

 

Introduction Rupa Tal (‘the Lake of Beauty’) lies in the Begnash and Rupa Lakes watershed area in the north-east of Kaski District in the midwestern region of Nepal. This area is about 150 km west of Kathmandu, within the co-ordinates: latitude 28°7’N to 82°12’N and longitude 84°5’E to 84°10’E.

 

At present Rupa Tal is undergoing sedimentation at a rapid rate, with the lake area being reduced from 194 ha to 115 ha between 1978 and 1995 (a loss of 40% in 17 years) (Oli, 1996). The present lake basin continues to receive sediments from the receiving streams to the northeast. The lake is fed from an upland stream (Dobhan Khola), and drains to the south through a small meandering channel (Tal Khola) to the Seti River. The southern margin of the lake has become a small marginal marsh, which drains the southern agricultural lands into the lake before entering the Tal Khola. In addition to these geo-physical changes, the present lake is highly eutrophic, with a considerable biomass of sub-surface and emergent macrophytes. It is probable that the deposition of weed peat will accelerate the sedimentation of the present lake area. Figure 1 gives a diagrammatic view of Rupa Tal and the existing areas affected by sedimentation.

 

Possible interventions Rupa Tal has traditionally been a major internal tourism area, and the local authorities are anxious that the beauty of the lake and its valley are preserved. The surrounding hills have been terraced along the lower slopes for rice production, and cropping now also occurs on the sedimented areas of the lake. To the south rice cultivation is dominant. The lake body provides a small degree of fishery income, including rudimentary cage aquaculture. The local authorities consider the rate of lake sedimentation to be an adverse phenomenon in respect of the preservation of the lake and the valley; and accordingly wish to consider possible interventions that might conserve a lake area and preserve the valley for tourism, agriculture and fisheries, as has been done elsewhere in this region of Nepal (NPC, 1995).

Four possible forms of action can be considered for the future possibilities in respect of the conservation of the lake area:

 

1.        No action, allowing the present sedimentation to continue, resulting in total loss    of the lake, and the creation of a small gorge to take the inflow/outflow streams.

 

2.        Building a high retaining dam along the southern margin to raise the overall water level (Figure 1: A-AA). This would be a major structure, and would inundate in-lake areas that have been created by sedimentation over the last few decades.

 

3.        Building a smaller, high dam set between two bluffs, about one third of the way up from the southern shore (Figure 1: B-BB). This partial dam would be a smaller construction than (2) but would have similar upstream effects.

 

4.        Either a single large sedimentation reservoir in the upstream area, or a series of smaller retaining walls, forming a sedimentation cascade (Figure 1: C-CC). This option allows solids to settle out well upstream of the present lake, and the present water area then will be able to remain intact.

 

 

Initial environmental evaluation To assist in the evaluation of these alternative options, the authors made a short three-day visit to Rupa Tal, and an initial environmental evaluation (IEE) was undertaken, using the Rapid Impact Assessment Matrix (RIAM).

Scoping was undertaken after a reconnaissance of the lake environments and observation of possible environmental problems related to changes in sedimentation. Local opinions were included in the scoping exercise, through discussions with the local people, members of the Village Development Council, and members and ex-members of the local authority and planning bodies.

 

The scoping exercise considered aspects of all four parts of an holistic environmental impact assessment: physical/chemical (P/C); biological/ecological (B/E); sociological/cultural (S/C); and economic/operational (E/O). Due the rapidity of the exercise and the need to make comparative evaluations in the absence of quantitative data, the final impact assessment is considered to an initial environmental evaluation (IEE) rather than a full environmental impact assessment (EIA).

 

The components chosen by the scoping exercise were used to compare the perceived impacts for all four development options defined above. These components are set out in Table 1.

 


 

 


Figure 1. Plan of Rupa Tal (not to scale)

 

 

Table 1. Rupa Tal. Selected components for IEE by RIAM

––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––

Physical/Chemical

P/C 1 Changes in lake water volume

P/C 2 Changes in lake sedimentation (measure of reduction of water surface)

P/C 3 Changes in crop and grazing areas

Biological/Ecological

B/E 1 Changes in lake fisheries

B/E 2 Changes in biodiversity

B/E 3 Changes in primary production

B/E 4 Changes in aquatic macrophytes

B/E 5 Changes in disease vector populations

Sociological/Cultural

S/C 1 Loss of housing

S/C 2 Loss of shops/public buildings

S/C 3 Changes to access routes

S/C 4 Changes induced by changes in tourism patterns

S/C 5 Changes to water supplies

S/C 6 Changes to diet/nutrition

S/C 7 Changes to aesthetic landscapes

S/C 8 Changes in water/vector borne disease

S/C 9 Changes to upstream quality of life

S/C 10 Changes to downstream quality of life

Economic/Operational

E/O 1 Changes in crop-generated incomes

E/O 2 Changes in fishery generated incomes

E/O 3 Ease of Operation & Maintenance of option

E/O 4 Cost of Operation & Maintenance of option

E/O 5 Cost of resettlement/compensation for land loss

E/O 6 Cost of rehabilitation/restoration of shops/public buildings

E/O 7 Cost of restoration of access routes

E/O 8 Changes in tourism-generated incomes

 

The physical/chemical components were restricted to those that related to the changes in lake water volume and the processes of sedimentation, with the concomitant changes in agricultural land that each option might cause.

 

Biological/ecological components reflected changes that might occur with each option in respect of the biota in the lake, specifically primary production, the change in aquatic macrophytes (secondary production) and finally changes in lake fisheries (including its ability to support aquaculture). In addition, the biodiversity of the southern margin marsh and the changes in insect disease vector populations were considered.

 

In considering the sociological/cultural components it was evident that each option provided different results to the present human settlement pattern of the area. Sedimentation has provided new land both for agriculture as well as houses and public buildings. Shops, temples and a school have been developed within the sedimented areas of the lake, and housing is found both in these areas as well as along the margins and higher reaches of the shores. This dwelling and development pattern has set the access routes to the area and these too would be affected by some options. The biological changes would have an impact on both diet and disease, and these two components are included. The aesthetic value of any option relates to tourism attractiveness, and this component together with an evaluation in the change in quality of life of the local communities completes this group.

 

The economic/operational components reflect the changes in agricultural, fishery and tourism incomes that might be expected from each option. The cost of mitigation in the form of rehabilitation of buildings and access routes is considered. Both the cost and complexity of the operations and maintenance of each option have been included in this group.

 

To complete the IEE, these components were evaluated using the Rapid Impact Assessment Matrix (RIAM). In this instance the RIAM used the following assessment criteria: Importance (A1), Magnitude (A2), Permanence (B1), Reversibility (B2) and Cumulation (B3). The results of the RIAM are set out in Table 2 for all the four options, and the final range values obtained from these results are summarised in Table 3 and Figure 2.

 

 

Table 2. Rupa Tal. RIAM results for each development option.

––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––

Option no. 1. No development

Evaluation Range

Values ascribed to RIAM criteria Score, Value

A1           A2           B1            B2            B3            ES            RV

–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––

P/C 1                       1              -3             3              3              1               _21         _C

P/C 2                       1              _2            3              3              1              _14          _B

P/C 3                       2              2              3              3              1                28            C

B/E 1                       1              _2            3              3              3              _18          _B

B/E 2                       1              _2            3              3              3              _18          _B

B/E 3                       1              _2            3              3              3              _18          _B

B/E 4                       1              _2            3              3              1              _14          _B

B/E 5                       1              1              3              3              3                 9             A

S/C 1                        1              0              1              1              1                 0             N

S/C 2                        1              0              1              1              1                 0             N

S/C 3                        1              1              3              2              1                 6             A

S/C 4                        1              _1            3              2              1                _6          _A

S/C 5                        1              _1            3              2              1                _6          _A

S/C 6                        1              0              1              1              1                 0             N

S/C 7                        1              _2            3              3              1              _14          _B

S/C 8                        1              1              3              2              3                  8            A

S/C 9                        1              0              1              1              1                  0            N

S/C 10                      1              _1            2              2              1                _5          _A

E/O 1                       1              2              3              2              3                16             B

E/O 2                       1              _2            3              3              1              _14           _B

E/O 3                       1              0              1              1              1                  0             N

E/O 4                       1              0              1              1              1                  0             N

E/O 5                       1              0              1              1              1                  0             N

E/O 6                       1              0              1              1              1                  0             N

E/O 7                       1              0              1              1              1                  0             N

E/O 8                       1              _1            3              1              1                _5            _A

 

 

 

 

 

 

Option no. 2. High dam on southern margin

A1           A2           B1            B2            B3            ES            RV

–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––

P/C 1                       1              2              3              3              1              14            B

P/C 2                       1              2              3              3              3              18            B

P/C 3                       1              _2            3              3              1              _14          _B

B/E 1                       2              2              3              3              3              36            D

B/E 2                       1              _1            3              3              3              _9            _A

B/E 3                       1              _2            3              3              3              _18          _B

B/E 4                       1              _2            3              3              3              _18          _B

B/E 5                       1              1              3              1              1              5              A

S/C 1                        1              _1            3              1              1              _5            _A

S/C 2                        1              _1            3              1              1              _5            _A

S/C 3                        1              _1            3              1              1              _5            _A

S/C 4                        1              2              3              2              1              12            B

S/C 5                        2              2              3              1              1              20            C

S/C 6                        1              1              3              1              1              5              A

S/C 7                        1              2              3              3              1              14            B

S/C 8                        1              _1            3              1              3              _7            _A

S/C 9                        1              1              3              1              1              5              A

S/C 10                      1              2              3              1              1              10            B

E/O 1                       1              _1            3              1              1              _5            _A

E/O 2                       1              2              3              2              1              12            B

E/O 3                       1              _1            3              3              1              _7            _A

E/O 4                       1              _1            3              3              1              _7            _A

E/O 5                       1              _2            2              1              1              _8            _A

E/O 6                       1              _1            2              1              1              _4            _A

E/O 7                       1              _1            2              1              1              _4            _A

E/O 8                       2              2              3              2              1              24            C

 

Option no. 3. High dam within existing lake

A1           A2           B1            B2            B3            ES            RV

–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––

P/C 1                       1              2              3              3              1              14            B

P/C 2                       1              _1            3              3              3             _9            _A

P/C 3                       1              0              3              1              1              0              N

B/E 1                       1              1              3              3              3              9              A

B/E 2                       1              _2            3              3              3              _18          _B

B/E 3                       1              _1            3              3              3              _9            _A

B/E 4                       1              _1            3              3              3              _9            _A

B/E 5                       1              1              3              3              1              7              A

S/C 1                        1              _1            3              1              1              _5            _A

S/C 2                        1              _1            3              1              1              _5            _A

S/C 3                        1              _1            3              1              1              _5            _A

S/C 4                        2              1              3              2              1              6              A

S/C 5                        1              1              3              2              1              6              A

S/C 6                        1              1              3              2              1              6              A

S/C 7                        1              1              3              3              1              7              A

S/C 8                        1              1              3              3              1              7              A

S/C 9                        1              1              3              3              1              7              A

S/C 10                      1              2              3              3              1              14            B

E/O 1                       1              2              3              1              1              10            B

E/O 2                       1              0              3              1              1              0              N

E/O 3                       1              _1            3              3              1              _5            _A

E/O 4                       1              _1            3              3              1              _7            _A

E/O 5                       1              _2            2              1              1              _8            _A

E/O 6                       1              _1            2              1              1              _4            _A

E/O 7                       1              _1            2              1              1              _4            _A

E/O 8                       1              1              3              2              1              6              A

 

 

 

 

 

 

 

 

 

 

Option no. 4. Upstream sedimentation reservoir/cascades

A1           A2           B1            B2            B3            ES            RV

–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––

P/C 1                       1              0              3              1              1              0              N

P/C 2                       1              2              3              3              3              18            B

P/C 3                       1              0              1              1              1              0              N

B/E 1                       1              0              1              1              1              0              N

B/E 2                       1              0              1              1              1              0              N

B/E 3                       1              0              1              1              1              0              N

B/E 4                       1              0              1              1              1              0              N

B/E 5                       1              _1            3              3              3              _9            _A

S/C 1                        0              0              1              1              1              0              N

S/C 2                        1              0              1              1              1              0              N

S/C 3                        1              0              1              1              1              0              N

S/C 4                        1              0              1              1              1              0              N

S/C 5                        1              1              3              2              1              6              A

S/C 6                        1              0              1              1              1              0              N

S/C 7                        1              0              1              1              1              0              N

S/C 8                        1              _1            3              1              1              _5            _A

S/C 9                        1              _1            3              1              1              _5            _A

S/C 10                      1              0              1              1              1              0              N

E/O 1                       1              0              1              1              1              0              N

E/O 2                       1              0              1              1              1              0              N

E/O 3                       1              _2            3              1              3              _14          _B

E/O 4                       1              _2            3              1              3              _14          _B

E/O 5                       1              0              1              1              1              0              N

E/O 6                       1              0              1              1              1              0              N

E/O 7                       1              0              1              1              1              0              N

E/O 8                       1              0              1              1              1              0              N

 

 

Table 3. Rupa Tal. Comparison of RIAM results

Option no.1             Option no. 2            Option no. 3            Option no. 4

–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––

P/C 1                       _C                            B                              B                              N

P/C 2                       _B                            B                              _A                           B

P/C 3                       C                              _B                            N                            N

B/E 1                       _B                            D                             A                             N

B/E 2                       _B                            _A                           _B                            N

B/E 3                       _B                            _B                            _A                           N

B/E 4                       _B                            _B                            _A                           N

B/E 5                       A                             A                             A                             _A

S/C 1                        N                             _A                           _A                           N

S/C 2                        N                             _A                           _A                           N

S/C 3                        A                             _A                           _A                           N

S/C 4                        _A                           B                              A                             N

S/C 5                        _A                           C                              A                             A

S/C 6                        N                             A                             A                             N

S/C 7                        _B                            B                              A                             N

S/C 8                        A                             _A                           A                             _A

S/C 9                        N                             A                             A                             _A

S/C 10                      _A                           B                              B                              N

E/O 1                       B                              _A                           B                              N

E/O 2                       _B                           B                              N                             N

E/O 3                       N                             _A                           _A                           _B

E/O 4                       N                             _A                           _A                           _B

E/O 5                       N                             _A                           _A                           N

E/O 6                       N                             _A                           _A                           N

E/O 7                       N                             _A                           _A                           N

E/O 8                       _A                           C                              A                             N

 

 

 

 

 

 

 


 


Figure 2. Rupa Tal.΄Numbers of each range value achieved using RIAM

 

 

 

 


Conclusions The IEE shows that the RIAM is an effective and rapid method to arrive at holistic comparison of strategic options in planning. The RIAM results presented very different project profiles for each option (Figure 2), from which it has been possible to provide an early indication of the merits of the various choices.

 

For option no.1 the RIAM analysis showed the expected negative impact due to complete sedimentation of the lake over time, with the commensurate improvement in available agricultural land. Negative impacts were associated with the deterioration in aesthetic value (the loss of the lake) and consequential expected downturn in tourism and related income. Some negative impact on water supplies was also suggested. Positive benefits were associated with improvement in access (over new ground); loss of water borne and insect disease vectors; and improvements in crop generated incomes.

 

Option no. 2 produced a very wide profile, and indicated the wide variety of issues that a large marginal dam would generate. On the positive΄side significant improvements were seen in respect of lake fisheries and incomes therefrom; water supplies to all communities should

improve; as would tourism  revenues. Improvements were seen to the problem of water vectors (by replacing a shallow, still water surface with a wave-creating deep lake), and to tourism related issues. Some improvement to the quality of life of all communities was expected in the longer term. Economic and operational factors, which were seen to be generally, negative, with a high initial loss of housing, public buildings and access. The conclusion for this option is that the very positive benefits in meeting the objectives of lake improvement would need to be set against the initial negative impact on local people, and the costs associated with mitigation of these impacts; together with the continuous high

cost of the operations and maintenance requirements.

 

Option no. 3 would show some cost improvements over option no. 2, but many of the larger positive benefits disappeared with this option, whilst the negative issues remained.

 

In option no. 4, most negative impacts reflect the high cost of operations and maintenance associated with clearing out and disposing of sediments accumulated by this system. As the present lake and its environs would be preserved, the status of the area and the communities dependent on it would remain largely unaltered from the present day. This lack of significant change has produced the largely neutral RIAM result.

 

The results of this rapid assessment provide useful guidance for possible future actions. A ‘do nothing’ situation will result in a complete loss of the lake, possibly via a phase of increased marshland and river formation in a relatively short period of time (if present sedimentation rates continue), and the RIAM has shown the impacts that such a situation

will generate.

 

To maintain the lake, there are effectively two technical solutions, represented by options no. 2 and 4. Option no. 3 has been discounted as a result of this IEE, as it provide little improvement in benefits over costs΄when set against option no. 2. If capital and running costs do not prove to be a major impediment to development, there is much to recommend

option no. 2. This option will nevertheless produce many initial changes, and a full EIA on this option would be needed to indicate the true scale of the positive/negative impacts identified. Option no. 4 offers the least change from the status quo, although the operational costs would need to be carefully considered. In terms of both cost and disruption, this IEE

suggests that option no. 4 is the solution most likely to be affordable and able to meet the objectives of preserving the character of Rupa Lake.

 

 

Acknowledgements The authors wish to acknowledge the considerable assistance provided to this evaluation by Mr Krishna Oli for his valuable background data on Rupa Tal, and for his help in logistical support in the field; as well as the number of local people who provided anecdotal information to assist in this assessment

 

References

NPC (National Planning Commission), 1995. Guidelines for Phewa Lake Conservation.

National Planning Commission/IUCN-World Conservation Union, HMG Nepal,

Kathmandu.

Oli, K.P., 1996. Conservation of the Mid-hills: Land use changes in Begnash and Rupa

Lake Watershed area, Nepal, 1978-1996, pers. comm., awaiting publication.